Construction Schedule

Construction Schedule

Due to specialized manufacturing requirements, Active Traffic Management (ATM) Gantries require an estimated 40 to 50 week manufacturing and delivery lead time. 

*Construction schedule is preliminary and subject to change.

Construction Begins

June 1, 2026

Substantial Completion

First Quarter 2027

ATM Gantry Installation

First Quarter 2028